Senate Standing Committee on Housing and Works convened a site visit and meeting under the Chairmanship of Senator Nasir Mehmood, alongside Senators Abdul Shakoor, Husna Bano, Jan Muhammad, Naseema Ahsan, Saifullah Abro, here on Thursday at the Islamabad Model Jail in Sector H-16, Islamabad, to review the physical progress, financial status, and operational readiness of the facility.
Senate panel reviews progress on Islamabad Model Jail

ISLAMABAD, Nov 19 (APP): Senate Standing Committee on Housing and Works convened a site visit and meeting under the Chairmanship of Senator Nasir Mehmood, alongside Senators Abdul Shakoor, Husna Bano, Jan Muhammad, Naseema Ahsan, Saifullah Abro, here on Thursday at the Islamabad Model Jail in Sector H-16, Islamabad, to review the physical progress, financial status, and operational readiness of the facility.

During the briefing, officials from the Capital Development Authority (CDA), the Ministry of Interior and Narcotics Control, and the Ministry of Planning, Development and Special Initiatives apprised the Committee that Phase-I of the project—approved under the second revised PC-I at a cost of Rs 7,399.12 million—has achieved 99 percent overall physical progress and 95 percent financial progress.
The Committee noted with satisfaction the substantial improvements observed since its previous visit and commended the authorities for the accelerated pace of work and compliance with earlier recommendations.
In reviewing the revised project scope, the Committee was informed that dedicated barracks for women and facilities for juvenile prisoners were excluded from Phase-I and shifted to Phase-II in order to enhance Phase-I capacity from 486 to 800 prisoners within the existing cost, addressing acute overcrowding at Adiala Jail pursuant to court and Prime Minister’s Office directives.
Regarding Phase-II, officials reported that preliminary documentation and consultant design work are currently underway, with an initial allocation of Rs 1 billion that will be enhanced over a projected one-year completion timeline.
Taking note of the pending Compliance Report required by the Central Development Working Party (CDWP), the Committee directed the relevant authorities to finalize the Phase-II PC-I and submit a comprehensive progress report prior to December 10.
During an extensive inspection of the facility, the Committee reviewed the command and control center, modernized kitchen and food storage areas capable of producing 600 rotis in a single batch with strict hygiene protocols, customized kitchen setups, emergency panic buttons, a skill development center, four designated courtrooms, and an on-site hospital staffed with doctors and nursing personnel available round-the-clock.
While appreciating these arrangements, the Chairman emphasized the immediate installation of surveillance cameras in the recreational play area to ensure prisoner safety and directed that the height of the barracks washroom walls be increased.
Furthermore, the Committee observed the absence of a mosque for inmates and on-duty staff, as well as the lack of an emergency room in the general visiting area, directing that work on the mosque commence before the next committee meeting and that the emergency room be completed on a priority basis.
The committee was briefed and attended by IG jails isb, CDA, planning and development department and all related and concerned officials.