Govt plans to add 15,206 MW of renewable energy capacity by 2035

ISLAMABAD, Nov 18 (APP):The government plans to add 15,206 megawatts (MW) of renewable energy capacity, including hydropower, to the national electricity generation system by 2035, accounting for approximately 93% of the total planned capacity additions during the 2025–35 period. According to official documents available with Wealth Pakistan, the National Electric Power Regulatory Authority (NEPRA) has approved the Integrated System Plan (ISP) 2025–35, envisaging total electricity generation capacity additions of 16,406 …

ISLAMABAD, Nov 18 (APP):The government plans to add 15,206 megawatts (MW) of renewable energy capacity, including hydropower, to the national electricity generation system by 2035, accounting for approximately 93% of the total planned capacity additions during the 2025–35 period.
According to official documents available with Wealth Pakistan, the National Electric Power Regulatory Authority (NEPRA) has approved the Integrated System Plan (ISP) 2025–35, envisaging total electricity generation capacity additions of 16,406 MW during the period.
Renewable energy projects, including hydropower, would contribute 15,206 MW, while the remaining 1,200 MW would come from nuclear power generation.
Providing a breakdown of the planned renewable energy additions, the document shows that hydropower projects would contribute 4,505 MW, solar photovoltaic projects under net-metering arrangements would add 8,120 MW, while wind power projects would contribute another 2,581 MW.
Of the planned wind power capacity, 1,190 MW would be added through the National Grid Company/National Transmission and Despatch Company (NGC/NTDC) network, while 1,391 MW would be integrated through K-Electric.
The country’s total installed electricity generation capacity is projected to reach approximately 62,383 MW by 2035, with renewable energy, including hydropower, accounting for more than 60% of the total installed capacity.
According to the document, the future capacity additions would be planned through the Indicative Generation Capacity Expansion Plan (IGCEP), based on least-cost system planning and implemented under the applicable policy and procurement framework.
The government has already established a policy framework through the National Electricity Policy 2021 and National Electricity Plan 2023–27, aimed at progressively increasing the share of renewable energy in the country’s installed generation capacity.
The policy framework envisages achieving a 60% renewable energy capacity share by 2030, with subsequent additions guided by system requirements, economic considerations and least-cost planning principles.
Currently, utility-scale renewable energy, including hydropower, accounts for approximately 35% of Pakistan’s installed generation capacity. However, the share of grid-connected renewable energy capacity exceeds 45% when distributed solar capacity connected through net-metering arrangements is included.
The IGCEP 2025–35 also assessed the requirement for battery energy storage systems (BESS) to support grid reliability, frequency response and the integration of increasing renewable energy capacity into the national electricity system.
The plan identified an indicative requirement of approximately 600 MW of BESS inverter capacity, supported by around 1,500 megawatt-hours (MWh) of energy storage, involving an estimated investment of $900 million to $910 million.
However, NEPRA has not approved the proposed battery storage investment at this stage and has excluded BESS from the approved Revised Base/Recommended Case. Instead, the regulator has directed the Independent System and Market Operator (ISMO) to undertake a comprehensive technical and economic assessment before considering its inclusion in future planning exercises.
The assessment would examine the actual storage requirement, optimal capacity, duration, technology, geographical location, operational applications, reliability requirements, costs and benefits, and overall cost-effectiveness of battery storage systems.
The study will also consider the potential deployment of consumer-level battery storage systems, with its findings expected to inform subsequent IGCEP and ISP planning exercises for NEPRA’s consideration.
Meanwhile, the National Grid Company has finalised a pilot 20 MW/20 MWh battery storage project at the Jhimpir-I grid station under Contract No. ADB-302-2021, with a revised project cost of $15.7 million.
An Asian Development Bank (ADB)-hired consultant is also associated with proposed battery storage projects comprising 500 MW (1,000 MWh) in the South under Phase-I and another 500 MW (1,000 MWh) in the North under Phase-II.
The first phase carries an approximate cost of $400 million and is expected to achieve commercial operation in FY2029–30, according to the document.