FGEHA accelerates F-14/15 development as major Infrastructure works enter full swing

Hina Durrani
ISLAMABAD, Feb 11 (APP):Federal Government Housing Authority (FGEHA), operating under the Ministry of Housing and Works, has significantly intensified construction activities in Sector F-14/15, marking a decisive phase in one of the capital’s most anticipated housing developments.
In a major push to fast-track progress, heavy machinery and workforce deployments have been scaled up, signaling the Authority’s renewed determination to meet development targets within the stipulated timeframe. Officials said that the project has now entered a “high-gear execution phase,” with visible on-ground activity expected to accelerate in the coming weeks.
An official spokesperson of FGEHA told APP that the development of basic infrastructure — including roads, sewerage systems, and electricity networks — is planned for completion within three years under the existing contract framework. However, he clarified that the timeline may be adjusted depending on operational factors, with extensions permissible under contractual provisions if required.
In a significant development, the National Logistics Cell (NLC) has formally mobilized at the site, bringing additional technical capacity and execution strength to the project. Authorities anticipate that development momentum will further intensify by the end of January, transforming the pace and scale of operations across the sector.
Addressing technical preparations, the spokesperson revealed that a comprehensive joint survey will be conducted during the first quarter to record natural surface levels. This will pave the way for extensive earthwork operations, including large-scale leveling and grading — a critical step toward laying the groundwork for modern urban infrastructure.
Responding to concerns regarding rising construction material costs, the official assured allottees that FGEHA had proactively incorporated an escalation factor into the project’s PC-1 planning document. “The financial framework already accounts for anticipated market fluctuations,” he said, underscoring the Authority’s foresight in financial planning.
On the issue of installment payments, the spokesperson disclosed that approximately 55 percent of allottees have cleared their third installment to date.
Regarding the possibility of an extension, he clarified that no formal decision has been made. “At present, the deadline has expired. Whether to grant further time or impose a penalty rests entirely with the Board,” he explained. He added that, so far, no penalties have been imposed, but the matter remains under consideration.
FGEHA reiterated that sustained cooperation from members remains essential to ensure timely achievement of project milestones. The Authority expressed appreciation for the continued trust of its allottees and reaffirmed its commitment to delivering a well-planned, fully serviced residential sector. For further information or assistance, members may contact FGEHA’s UAN at 051-111-134-342 during official working hours.