Decision on Kalabagh Dam only with provinces’ consent: Sanjrani

Decision on Kalabagh Dam only with provinces’ consent: Sanjrani
File Photo

ISLAMABAD, Sep 15 (APP): Chairman Senate Sadiq Sanjrani on Tuesday said that no one can make any decision on construction of Kalabagh Dam without permission from provinces and approval from Council of Common Interests (CCI).

Giving his ruling on the matter in the Upper House of the parliament on raising objections from the senators of opposition, he said that no work is possible on the project without having consent from provinces.

Assuring the house on making any such decision without discussing the matter in the relevant forum, Adviser to Prime Minister on Parliamentary Affairs Dr Babar Awan and Minister for Parliamentary Affairs Ali Muhammad dispelled the impression of making decision without approval from provinces.

In a written reply, Minister for Water Resources Muhammad Faisal Vawda said that WAPDA has prepared a comprehensive plan to address the water scarcity issue by storing flood water during high flow season and utilize the same during lean season.

He said that the federal government is providing funds for construction of 60 small, medium, large and delay action or recharge dam projects in the country through Federal Public Sector Development Program. These projects aim to provide water for irrigation, agriculture, and drinking purposes.

He said that it is a fact that per capita water availability in Pakistan in 1951 was 5,260 m3 per annum, which is constantly decreasing and at present has reduced to less than 1,000 m3 per annum per capita due to increasing population, which is the stage of water scarcity.

Sharing details about Diamer-Basha Dam, Faisal Vawda said that so far 32,139 acres (86%) of land has been acquired out of total required land of 37,419 acres and the construction of one number Resettlement Model Village at Harpan Das is in progress with overall progress of 95%.

He said that construction of Project Colony at Thor is in progress while construction of Right Bank Periphery Road is under process. He added two contracts RBPR-01 and 02 have been awarded and the progress achieved is 68.50% and 40% respectively.

He said that the procurement of Contractor for RBPR-03 04 is in progress while the construction of Shatial Thor Nullah Bypass (42 km) by NHA as deposit work is in progress with 51% overall progress.

He said that 3.6 MW Thor Hydropower Project is operational since June 26, 2019. Electricity is being supplied to locals as goodwill gesture till commencement of work on main dam.

He said that 3.0 MW Thak Powerhouse is under construction and progress is 94%. He said that for procurement of Consultancy Services for Construction Design, Construction Supervision and Contract Administration, the Contract for Consultancy Services was signed on May 11, 2020.