The Balochistan High Court (BHC) has issued a series of significant directives aimed at addressing Quetta’s growing traffic congestion, illegal parking, encroachments, public transport challenges and environmental pollution during the hearing of Constitutional Petition No. CP-1951/2022.
BHC issues key directives to address traffic, encroachments, pollution in Quetta

QUETTA, Nov 29 (APP): The Balochistan High Court (BHC) has issued a series of significant directives aimed at addressing Quetta’s growing traffic congestion, illegal parking, encroachments, public transport challenges and environmental pollution during the hearing of Constitutional Petition No. CP-1951/2022.
A two-member bench comprising Chief Justice Muhammad Kamran Khan Malakhail and Justice Muhammad Najamuddin Mengal reviewed progress reports submitted by relevant government departments and ordered authorities to accelerate measures for improving urban traffic management and public transport infrastructure in the provincial capital.
During the hearing, the Additional Advocate General informed the court that a meeting chaired by the Commissioner Quetta Division on 12 November 2026 had directed authorities to remove encroachments and illegal parking stands from newly constructed and expanded roads across the city.
Particular emphasis was further informed that a committee had been constituted to conduct a detailed survey of six major roads in Quetta to identify illegal commercial activities, unauthorized constructions and encroachments.
Authorities have also been instructed not to approve any new commercial or construction projects without approved building plans, compliance with building regulations and adequate parking facilities.
Officials from the Transport Department told the court that the revised PC-I for a project aimed at replacing motor rickshaws with electric vehicles in Quetta’s Central Business District had been approved by the Provincial Development Working Party (PDWP). The project cost was revised downward from Rs595.72 million to Rs503.45 million, paving the way for implementation.
The court was also informed that land designated for the construction of a Smart Local Bus Stand had been cleared of illegal occupants who had been operating workshops, showrooms and other commercial activities on the site. To secure the land against future encroachments, the Transport Department has requested the Communications and Works Department to prepare estimates for the construction of a boundary wall.
During proceedings, officials reported that a meeting chaired by the Advocate General Balochistan on 25 November 2026 had decided to ensure the delivery of approved pink electric scooters on 2 December 2026 through a joint team at the Balochistan High Court parking area.
However, representatives of the High Court Bar Association informed the court that two diesel buses for Kuchlak and Sariab, two pink vans for Khuzdar and Pishin, and two electric shuttle carts had yet to be delivered. Authorities responded that work orders for the required vehicles had already been issued.
Petitioners Shermeen Rehman and Anam Khair, both advocates, urged the court to prioritize electric or hybrid buses and vans instead of diesel-powered vehicles to reduce environmental pollution and associated public health risks.
According to a report submitted by the SSP Traffic Quetta, traffic police have completed the auction of 476 abandoned and scrap rickshaws, generating Rs17.357 million, which has been deposited with the Accountant District Court.
The report further highlighted ongoing enforcement operations against traffic violations, unfit public transport vehicles, tinted windows, fancy number plates and illegal parking on double roads.
To strengthen traffic management, authorities have deployed 15 Suzuki Swift vehicles equipped with GPS tracking and live-camera systems, along with 10 patrol motorcycles. An additional 10 motorcycles have also been provided for traffic patrolling duties across the city.
After reviewing all progress reports and objections raised by petitioners, the High Court issued several directives to concerned authorities.
The court instructed the Additional Chief Secretary Development to ensure approval of the PC-I for the boundary wall around the Smart Bus Stand site. The Regional Transport Authority was directed to prepare and submit a revised PC-I for the bus stand project to the Planning and Development Department without delay so that civil works could begin immediately after approval.
The Inspector General of Police and DIG Quetta were ordered to provide security for the site through the relevant SP and SHO until construction of the boundary wall is completed. The Transport Department was also directed to deploy personnel to prevent any future illegal occupation or encroachment.
The court further ordered authorities to prioritize the procurement of electric or hybrid buses and vans, taking environmental considerations into account, while also ensuring the delivery of approved pink electric scooters for members of the High Court Bar Association.
Additionally, the Secretary Finance was instructed to address issues relating to incentive payments for traffic police personnel under the Provincial Motor Vehicles (Amendment) Ordinance, 2002, and to prioritize funding for approved transport projects, including electric shuttle carts intended for Quetta’s central business district.
The Advocate General’s Office and the Additional Advocate General were directed to communicate the court’s orders to all concerned departments and ensure implementation. Relevant officials, including the Secretary Finance, have been ordered to submit compliance and progress reports at the next hearing.
The court subsequently adjourned further proceedings in the case until 10 December 2026.