Work on the Margalla Avenue extension from N-5 to M-1 and the Sangjani Interchange has reached 41 per cent completion, with construction activities continuing round the clock, according to the Capital Development Authority (CDA).
Margalla Avenue extension, Sangjani interchange 41pc complete

ISLAMABAD, Nov 17 (APP): Work on the Margalla Avenue extension from N-5 to M-1 and the Sangjani Interchange has reached 41 per cent completion, with construction activities continuing round the clock, according to the Capital Development Authority (CDA).
CDA Chairman and Chief Commissioner Islamabad Sohail Ashraf reviewed the progress of the projects during a site visit on Tuesday and directed the concerned officers to ensure their timely completion while maintaining construction quality.
Officials briefed him that work was under way on a 2.7-kilometre extension of the main road within Islamabad Capital Territory (ICT) limits, along with loops, ramps and connecting service roads.
The structural work on the underpass has been completed, including its concrete walls and footing slabs, while piling work at the Sangjani Interchange has also been finished. Girder launching is expected to begin soon.
Officials further said piling and excavation work for abutments on both sides of the N-5 bridge had been completed. Construction of four culverts was also finished, while work on another was in progress.
Sohail Ashraf said the project would serve as an important gateway for people traveling to Islamabad from other cities, particularly Khyber Pakhtunkhwa, and improve connectivity within and outside the federal capital.
He directed the project team to maintain construction standards and complete the work within the stipulated time-frame.