The Capital Development Authority (CDA) is developing an 860-kanal graveyard in Pandorian to address the growing shortage of burial space in the federal capital, with 70 per cent of the project completed so far.

ISLAMABAD, Nov 16 (APP): The Capital Development Authority (CDA) is developing an 860-kanal graveyard in Pandorian to address the growing shortage of burial space in the federal capital, with 70 per cent of the project completed so far.

Islamabad to get 860-kanal graveyard amid shortage of burial space

The authority expects to complete the remaining construction work by the end of this year, providing residents with an additional facility for burials.

According to a CDA spokesperson on Monday, 95 per cent of government land earmarked for the project has been retrieved, while action against illegal constructions and encroachments is under way to clear the remaining land.

The project includes a spacious parking area, a boundary wall, an administrative block and a funeral hall (Janazah Gah). The grey structure of the administrative block has been completed, while roofing and finishing work on the funeral hall is in progress.

Light poles have been installed across the site, while utility-related work is around 50 per cent complete. The authority also plans to introduce environmentally friendly plantation and permanent lighting arrangements.

CDA Chairman Sohail Ashraf has directed the relevant teams to complete the project within the current year while maintaining construction standards.